17-09-2019, 05:33 PM
(18-06-2019, 08:05 PM)davestretton Wrote:(18-06-2019, 07:57 PM)Paplane Wrote: I was wondering what was holding the planning application up. I guess it's the negotiations re the lease.
They need to get their finger out if they're hoping to start work next spring.
Planning application is not due to be submitted until the end of next month, and subject to approval, work will begin next summer
Dave, any more you can say on the progress of the planning app? Surely it's getting tight now for a spring start? There's the planning (12 weeks determination period then likely planning committee(?)), plus prep of tender docs and contractor tendering (or negotiating), plus detailed technical design.